A request for quotation (RFQ) is a formal document a buyer sends to selected suppliers asking for a price, lead time and terms on a clearly specified product or service. Because the requirement is already defined, suppliers compete mainly on price, delivery and commercial terms rather than on the solution itself.
Key facts
- An RFQ is used when you know exactly what you need, including specification, quantity and delivery point.
- Most industrial buyers invite three to five suppliers so that pricing is genuinely competitive.
- An RFQ asks for a price; an RFP asks for a proposed solution; an RFI asks for general information.
- A strong RFQ states the specification, quantity, delivery terms, deadline and evaluation basis.
- Quotations should be compared on total landed cost, not unit price alone.
- The process ends with a purchase order or contract awarded to the selected supplier.
In short, a request for quotation turns a defined requirement into comparable, binding offers. The buyer writes a precise specification, sends it to qualified suppliers with a fixed response deadline, compares the returned quotations on price, lead time, compliance and total cost, clarifies any gaps, and awards a purchase order. Done well, an RFQ cuts cost, shortens sourcing time and creates an audit trail that explains why a supplier was chosen.
What is a request for quotation?
An RFQ sits at the point in the procurement cycle where the need is understood and the market is ready to be tested. The buyer is not asking suppliers to design anything. Instead, the buyer says: here is the part number, the material grade, the quantity and the delivery location, so tell us what you would charge and how quickly you can ship.
In industrial, energy and oilfield settings, typical RFQ items include valves, flanges, pipe and fittings, pumps, spare parts, consumables, safety equipment and standard services such as inspection or equipment hire. These are items where several suppliers can deliver the same specification, so the decision comes down to commercial terms and reliability.
The response from a supplier is called a quotation (or quote). An RFQ is the question; the quotation is the answer. Once the buyer accepts a quotation, usually by issuing a purchase order, the offer becomes a contract on the stated terms.
RFQs were traditionally sent by email or post, with quotes returned as attachments that the buyer then retyped into a spreadsheet. Today, many buyers use e-procurement tools or online marketplaces instead. These publish the enquiry once, collect quotations in a consistent format and keep a time-stamped record of every response, which makes comparison and audit much simpler.
When to use an RFQ
- The specification is fixed and can be written down without ambiguity.
- Several suppliers can meet the same requirement.
- Price and lead time are the main differences between offers.
- Your organisation's policy requires competitive quotes above a spending threshold.
If you cannot yet describe the solution, an RFQ is premature. Start with an information request or a proposal request instead, as the next section explains.
RFQ vs RFP vs RFI: which one do you need?
Buyers often use these terms interchangeably, but they serve different purposes. Choosing the wrong one wastes supplier effort and produces responses you cannot compare. The table below sets out the differences.
The common sequence on larger projects is RFI, then RFP, then RFQ. An RFI builds a long list of capable suppliers. An RFP narrows the approach. An RFQ then prices the agreed specification. For routine purchases such as replacement parts, buyers usually go straight to an RFQ.
A related question is RFQ vs quotation. The RFQ is issued by the buyer; the quotation is issued by the supplier in response. Some organisations also use the term request for tender, which is broadly a formal RFQ or RFP run under strict public or corporate rules with sealed bids.

The request for quote process in 7 steps
Whatever the size of the purchase, a disciplined RFQ follows the same seven steps. Skipping any of them is where most delays and disputes start.
- Define the requirement. Confirm the specification, quantity, required-by date and delivery location with the end user or engineering team.
- Select suppliers to invite. Use an approved supplier list, past performance or a verified marketplace to choose three to five qualified suppliers.
- Prepare the RFQ document. Write the specification, commercial terms, response format and deadline in one clear package.
- Issue the RFQ and manage questions. Send it to all invited suppliers at the same time and share answers to clarification questions with everyone.
- Receive and evaluate quotations. Check each quote for compliance, then compare on total cost, lead time and risk.
- Clarify and negotiate. Resolve exceptions, confirm assumptions and, where policy allows, negotiate with the preferred supplier.
- Award and close. Issue the purchase order, notify unsuccessful suppliers and file the evaluation for audit.
Single-stage vs two-stage RFQs
Most RFQs are single-stage: suppliers submit technical and commercial details together, and the buyer evaluates both at once. For engineered or safety-critical items, many organisations prefer a two-stage approach. Suppliers first submit a technical offer, which engineering reviews for compliance. Only suppliers who pass are then asked for, or have opened, their commercial offer.
The two-stage method takes longer, but it stops a low price from influencing the technical review. It also avoids wasting commercial effort on offers that would fail inspection anyway.
Steps one and two are often rushed, yet they decide the quality of everything that follows. A vague requirement produces quotes that cannot be compared, and an unqualified supplier list produces cheap offers that fail at inspection. The wider cycle around these steps is covered in our guide to the seven steps of the procurement process.
How to write an RFQ that gets accurate quotes
Suppliers can only price what you describe. A good RFQ removes guesswork so that every supplier quotes on the same basis and you can compare offers line by line.
What to include: an RFQ template checklist
- Buyer details and reference number so suppliers can quote against a unique enquiry.
- Item description with part numbers, material grades, sizes, pressure or temperature ratings and drawings where relevant.
- Quantity and unit of measure, including whether partial quantities may be quoted.
- Required certification and documentation, such as material test certificates, inspection reports or certificates of conformity.
- Delivery location and agreed trade terms, stating who pays for freight, insurance and import duties.
- Required delivery date and whether partial shipments are acceptable.
- Payment terms and validity period, for example quotes valid for 30 days.
- Response format and deadline, ideally a pricing table suppliers must complete.
- Evaluation basis, so suppliers know whether price, lead time or quality carries most weight.
Common mistakes to avoid
The most frequent error is an incomplete specification, which invites suppliers to quote the cheapest interpretation. Another is an unrealistic deadline that excludes good suppliers. Buyers also forget to state delivery terms, then discover that one quote includes freight and another does not. Finally, sending different information to different suppliers undermines fairness and makes the comparison meaningless.
If you want to see how a clear enquiry is structured in practice, you can submit an RFQ on BSO and verified suppliers will quote against the same specification.
How to evaluate and compare quotations
Once quotations arrive, resist the urge to sort by price and pick the lowest. A quote that looks cheapest can become the most expensive once freight, duties, late delivery or rework are added.
Start with a compliance check. Does the quote meet the specification, include the required certificates and accept your key terms? Any quote with material exceptions should be clarified or set aside before commercial comparison.
Next, compare on total landed cost. This includes unit price, packing, freight, insurance, duties and any inspection or documentation charges. For example, a supplier quoting 12,000 units at a slightly higher unit price but including delivery to site may beat a lower unit price quoted ex-works.
Then weigh the non-price factors:
- Lead time and the supplier's confidence in meeting it.
- Track record on quality and on-time delivery.
- Payment terms and their effect on cash flow.
- Risk, including single-source dependence and geographic exposure.
Many organisations use a simple weighted scoring matrix, agreed before the RFQ is issued, so the decision is objective and defensible.
Write your scoring weights down before the first quote arrives. Once you have seen the prices, it is far too easy to adjust the weights to justify the answer you already prefer.

How suppliers should respond to an RFQ
For suppliers, an RFQ is a direct invitation to win business, and the quality of the response often matters as much as the price. Buyers favour quotes that are easy to evaluate and leave nothing to interpret.
- Answer the question asked. Use the buyer's pricing format, line numbers and units of measure.
- State exceptions clearly. If you cannot meet a requirement, say so and offer an alternative rather than staying silent.
- Be explicit about lead time. Give a realistic delivery date from order and note any dependencies.
- Include documentation. Attach data sheets, sample certificates and relevant approvals.
- Confirm validity and terms. State how long the price holds and which trade terms apply.
- Respond on time. Late quotes are often excluded, however competitive they are.
Suppliers who want a steady flow of opportunities can monitor the open enquiries board, where buyers publish live RFQs for industrial and oilfield products. Responding quickly with a complete, compliant quotation is the most reliable way to build a reputation with new buyers.
Price with the buyer's total cost in mind. If you can include delivery to site, consolidate items into one shipment or hold stock for call-off orders, say so. These options often matter more to an industrial buyer than a small reduction in unit price, because they reduce the buyer's own handling, freight and administration.
It also pays to ask clarification questions early. A short question on day one is far better than a qualified quote on the deadline that the buyer cannot compare with the others.
Delivery, logistics and next steps
An RFQ for goods is only half complete if delivery is left to chance. For heavy, oversized or international shipments, freight can be a significant share of total cost and the main cause of delay. Many buyers therefore run a separate logistics RFQ once the goods supplier is selected, asking freight forwarders and hauliers to quote on collection, transport, customs clearance and delivery to site.
To make a logistics quote accurate, share the collection and delivery addresses, packed dimensions and weights, the number of packages, any dangerous goods classification and the required delivery window. On BSO, buyers can publish shipments to the logistics board so that logistics providers quote against the same details.
Before awarding any RFQ, make sure the supplier itself has been properly checked. Our supplier due-diligence checklist covers how to verify registration, certification, financial health and track record.
Finally, close the loop. Record why the winning quote was chosen, give brief feedback to unsuccessful suppliers and track delivery performance against the quote. Over time, this data makes every future request for quotation faster and better informed. To see how enquiries, quotations and logistics fit together on one platform, read how BSO works.
Frequently asked questions
Start with a precise specification, including part numbers, material grades, quantity and drawings. Add delivery location, trade terms, required date, certification, payment terms and quote validity. Provide a pricing table for suppliers to complete, set a clear deadline and state how quotes will be evaluated. Send the same request for quotation to every invited supplier at the same time.
An RFQ, or request for quotation, is the document a buyer sends asking suppliers for prices on a defined requirement. A quotation is the supplier's reply, stating the price, lead time, validity and terms on which it will supply. The RFQ is the question and the quotation is the answer; accepting a quotation, usually through a purchase order, creates the contract.
A request for quotation asks suppliers to price a requirement that is already fully specified, so offers differ mainly on price, lead time and terms. A request for proposal asks suppliers to propose how they would meet a need, so responses differ in approach as well as cost. Use an RFP when the solution is open and an RFQ when it is fixed.
The seven steps of a request for quotation process are: define the requirement, select qualified suppliers to invite, prepare the RFQ document, issue it and manage clarification questions, receive and evaluate quotations, clarify and negotiate with the preferred supplier, and award the purchase order while notifying unsuccessful bidders and filing the evaluation for audit.
Many organisations invite three to five qualified suppliers to each request for quotation. Fewer than three can limit competition, while sending it to too many wastes supplier effort and makes evaluation slower. For high-value or specialised items, internal policy may set a minimum number of quotes, so check your organisation's procurement rules before issuing the RFQ.
For standard catalogue items, a response window of a few working days is common, while complex or engineered items may need two weeks or more. Give suppliers enough time to check stock, confirm lead times and gather certificates. An unrealistically short deadline on a request for quotation excludes good suppliers and produces rushed, heavily qualified quotes.